« All Development Applications
TUP 20-002
Issued
Result
RD/20/09/47
MOVED Director Rose, SECONDED Director Bumstead,
That the Regional Board authorize the issuance of Temporary Use Permit No. 20-002, to allow a ±12.16 hectare area of Units 19 & 29 Block, Group 93-P-11, Peace River District, to be used as a pipeline construction stockpile site and laydown yard for a three year term, expiring September 10, 2023.
AMENDED BY THE FOLLOWING
RD/20/09/48
MOVED Director Bumstead, SECONDED Director Ackerman,
That the motion be amended to add:
“, with the condition that the proponent escort school buses along the Lone Prairie route to enhance traffic safety.”
to the end of the resolution. CARRIED
The Chair called the Question to the Motion as Amended:
That the Regional Board authorize the issuance of Temporary Use Permit No. 20-002, to allow a ±12.16 hectare area of Units 19 & 29 Block, Group 93-P-11, Peace River District, to be used as a pipeline construction stockpile site and laydown yard for a three year term, expiring September 10, 2023, with the condition that the proponent escort school buses along the Lone Prairie route to enhance traffic safety. CARRIED
Overview
Applicant: Coastal GasLink Pipeline Ltd.
Summary: Proposed temporary 12.16 ha Stockpile Site to support pipeline construction activities on Crown Land along the Lone Prairie Road
Electoral Area: Area E
Provide Input
All written submissions must be received by the PRRD 4:00 pm the day before the Regional Board meeting, alternatively you may attend and provide input at the beginning of the meeting.
Submit Comment
Deadline: September 9, 2020 4:00 pm
Comment Period Closed
Status Updates
Apr 28, 2020
In progress